A military cargo truck, soldiers and port workers at the container terminal in Gdańsk, Poland.
ECO EFX Solutions · Defence & military logistics

What does it cost to fuel an armed force?

Tanks, supply trucks, field power, ships and aircraft draw on the same public budget. Their fuel accounts need different units of measure.

Start with the service the fuel buys

A finance director can see what the fuel invoice cost. It takes an operating record to explain why it changed. A tracked vehicle covering soft ground, a generator delivering electricity overnight and a ship alongside all consume fuel under different conditions. For a budget review, pair the volume issued with distance, hours or electricity delivered. Keep the fuel grade, location and contract price alongside each entry.

Land forces: the terrain belongs next to the number

Three public equipment references illustrate the range of demand on land. They describe particular vehicles and conditions. They cannot be used to rank forces or to forecast a mixed fleet without its activity records.

EquipmentPublished consumptionWhat the figure covers
Leopard 2 main battle tankAbout 700 L/100 kmBundeswehr, 2023: off-road driving. This is not a road or annual fleet average.
Bundeswehr · Leopard 2, 2023 ↗
Marder tracked infantry fighting vehicle130–400 L/100 kmGerman Defence Ministry, November 2021, pp. 10–11: range for road and cross-country use. The mix of the two is unspecified.
German Ministry of Defence · equipment catalogue, 2021 ↗
GBC 180 supply truck, 6×630 L/100 kmFrench Army, 2011: equipment data sheet. Payload, terrain and test cycle are not stated.
French Army · GBC 180, 2011 ↗

For tracked fleets, record distance and stationary engine hours separately. For supply fleets, add payload, empty return journeys and the tonnes delivered. A lower fuel bill can simply reflect fewer deliveries.

Field power: budget by load and running time

How much does a generator use while it is running? The answer needs a load. These manufacturer figures apply to five Cummins AMMPS sets at 100% rated electrical output, using the 50/60 Hz models. Part-load use cannot be inferred by drawing a straight line from zero.

Fuel use at full load · litres per operating hour
5 kW1.63 L/h10 kW2.84 L/h15 kW4.01 L/h30 kW9.31 L/h60 kW16.92 L/h

Calculated from the original US gallons per hour; figures rounded. The machine sizes differ. For procurement, compare fuel per usable kWh at the loads a site actually needs, with its reserve capacity intact.

Cummins · AMMPS specifications, 2019 ↗

One 60 kW set at four loads

Sandia National Laboratories fitted a curve to diesel consumption for a 60 kW AMMPS set. These calculated points show how fuel demand changes as the same generator delivers more power. They are not individual meter readings.

Electrical loadElectrical outputFuel per hourFuel per kWh
25%15 kW5.89 L/h0.392 L/kWh
50%30 kW9.55 L/h0.318 L/kWh
75%45 kW13.21 L/h0.294 L/kWh
100%60 kW16.88 L/h0.281 L/kWh

Sandia National Laboratories · SAND2021-14967, Fig. 5 ↗

A worked fuel bill: one 30 kW generator

Assume 1,000 hours at full load and the use of DS2 diesel. At the published rate of 2.46 US gal/h, consumption is 2,460 US gallons. The US Defense Logistics Agency’s standard price effective 1 October 2025 was USD 3.56 per US gallon of DS2: the resulting fuel budget is USD 8,757.60. This dated US tariff is not a local pump price or a forecast.

Cummins · AMMPS specifications, 2019 ↗ · US Defense Logistics Agency · DS2 tariff, 1 October 2025 ↗

At the US Energy Information Administration’s diesel combustion factor of 10.19 kg CO₂ per US gallon, that volume gives about 25.07 tonnes of direct CO₂. Extraction, refining and delivery are outside this boundary. An internal carbon price is a separate planning assumption; it does not by itself create a payment obligation.

US Energy Information Administration · combustion factors, 2024 ↗

United Kingdom: four years of equipment fuel use

UK Ministry of Defence actuals by financial year, in millions of litres. Aviation, maritime and ground are shown separately; the small “other fuels” category is excluded from this chart. The table gives the same figures at higher precision.

United Kingdom: four years of equipment fuel use · 10⁶ L
  • Aviation
  • Maritime
  • Ground
Financial yearAviation (10⁶ L)Maritime (10⁶ L)Ground (10⁶ L)
2022/23371.581166.78834.384
2023/24311.757180.26325.198
2024/25270.805127.15930.865
2025/26262.966161.73930.201

Costs and emissions

In 2025/26 the UK reported £362.742 million in equipment fuel expenditure, down from £395.114 million in 2024/25. Over the same period, reported Scope 1 capability emissions rose from 1.164 to 1.250 million tonnes CO₂e. These are aggregate figures with their own reporting boundaries. They are not a carbon factor for any individual ship or vehicle.

Financial yearFuel expenditure (10⁶ GBP)Scope 1 capability emissions (10⁶ t CO₂e)
2022/23346.2951.569
2023/24445.2941.485
2024/25395.1141.164
2025/26362.7421.250

UK Ministry of Defence · annual accounts 2025/26, Annex D ↗

Where a budget holder can act

What should a defence ministry’s budget office report?

For a fleet or generator budget review, reconcile purchases with opening and closing fuel stocks. Then show separately how much of the spending change came from the unit price, the volume used and the activity delivered. For generators, compare fuel per kWh at comparable loads.

In the budget submission, identify the appropriation affected, who pays for the change and when any reduction in expenditure would reach that budget. Show direct CO₂ alongside the financial result. Keep an internal carbon valuation separate from a charge actually paid.

Reconcile procurement and usage

Match invoices and fuel issues to opening and closing stocks. Identify changes in purchase price, delivery costs and activity before attributing a variance to efficiency.

Compare equal service

Test generator sizing against a measured load profile; review idling by vehicle type and shore power against the cost and emissions of onboard generation. Protect the required availability and power reserve.

Verify a change before funding it

Agree the baseline, comparison period, service output and measurement uncertainty in advance. Include implementation cost and report adverse results. A product claim is not a budget saving.

Discuss technology use for your vehicles and equipment

Describe the general types of vehicles, generators and equipment concerned, their engines and typical operating conditions. Discuss with our team what information is needed to assess a potential application.

Discuss potential applications